Example of a typical scope of supply
- 146 panels of VEDA low-voltage switchboards
- 120 panels of free-standing cabinets
- 150+ pcs of control boxes
- 300+ pcs of frequency converters
- 9 pcs of distribution transformers
Sailing in the Mediterranean or the Caribbean
The delivery to MEYER WERFT has taken VEO’s marine business to a whole new level. Half of the ships will be built at MEYER WERFT’s shipyard in Papenburg, Germany, while the other half will be built at the company’s Turku shipyard in Finland. When completed, these ships will sail either in the Mediterranean or the Caribbean Sea.
Project status
Ship 1: S.696 AIDA nova – Handed over
Ship 2: NB1394 Costa Smeralda – Handed over
Ship 3: S.710 IONA – Handed over
Ship 4: NB1396 Mardi Gras – Handed over
Ship 5: (option) S.709 AIDA cosma – Delivery of VEO’s part
Ship 6: (option) NB1395 Costa Toscana – Delivery of VEO’s part
Ship 7: (option) S.716 Arvia – In progress
Ship 8: (option) NB1397 Carnival Celebration – In progress
Ship 9: (option) S.717 Carnival – In progress
Smooth and timely deliveries
VEO has successfully delivered its part of the project according to schedule and everything has run smoothly. Before this massive project, MEYER WERFT was a new VEO customer, which meant that small adjustments had to be made in accordance with customer specific needs. Now, with several successfully completed deliveries, VEO has become one of MEYER WERFT’s trusted partners, with a good concept for project management in large-scale cruise liner projects.
Opportunity for extensive FATs, also online
In such projects, VEO and the customer set up different milestones concerning design, approval, procurement, manufacturing, testing, packing & delivery as well as for Factory Acceptance Tests (FAT). When it comes to FATs, VEO has high-quality testing facilities at its factory in Vaasa where even extensive FATs can be run safely. By running FATs for all our electrification and automation interfaces, we can ensure that errors are eliminated before delivery, which saves valuable time when commissioning onsite. Our FATs also help to maintain our prized safety-at-work policy when delivering electrification and automation solutions to our customers.
We have also taken remote FATs into use, which give our customers the possibility to join the tests more efficiently and safely online, through live video.
Cooperation throughout the project
VEO continues to work closely with the customer, even after the successful delivery of VEO’s products, by making requested design modifications and working with the modified switchboard installations at the yard. The duration of one cruiser line project is more than 2 years from the kick-off meeting to the final hand over.